A 40-megawatt solar farm in the Mackenzie District is the project Far North Solar Farm Ltd has been pursuing consent for. The renewable energy developer, whose directors are Richard Homewood and Melbourne-based John Telfer, has now entered receivership.
Under a General Security Deed, joint receivers Stephen Keen and Stephen White of Teneo Financial Advisory New Zealand were appointed on 18 November. Aquila Clean Energy SG Holdco Pte. Ltd appointed them, taking control of the developer’s assets so money owed under a 2021 agreement can be recovered.
The project at the centre of the receivership is known as The Point and sits along the northern shore of Lake Benmore. It was one of a wave of solar developments proposed for the Mackenzie District, and its collapse into receivership leaves the consent process in the hands of a secured creditor rather than the developer.
The General Security Deed behind the appointment related to a joint venture between Far North Solar Farm and Aquila. The two businesses had worked together on the Pukenui solar farm in Northland, which the venture commissioned.
The arrangement was disbanded in January. Aquila’s website said the split allowed both parties to pursue their respective strategic priorities independently, and that the companies agreed to divide ownership of proposed projects. Far North Solar Farm took the developments in Greytown, the Mackenzie, and other parts of the South Island.
That division of assets means the Mackenzie project sat with the developer now in receivership, while Aquila retained other schemes. The receivership notice does not set out the size of the debt owed to Aquila.
The receivership follows a difficult period for the consent process. Far North Solar Farm applied to the fast-track process last October to build the solar farm on the lake’s northern shore.
Facing an August 31 deadline for expert ecological information, the company told the fast-track panel in August that outstanding invoices would go unpaid. Only that way, in its account, could it secure more planning time.
The Environmental Protection Authority set no timeframe for repaying the fees when it suspended the application. At the time, Far North Solar Farm stated its intention to pay its fees and progress the project.
The move drew criticism from Twizel residents. Mary Murdoch, a spokesperson for a community group set up to inform residents about developments in the district, said the developer appeared to be gaming the system rather than using it as intended. The company firmly denied that characterisation.
Solar farm proposals put forward for the Mackenzie District were on the agenda when the Twizel working group first met in August. Residents discussed introducing specific land overlays to protect natural landscapes, as well as forming sustainability coalitions like those seen in Southland and Queenstown.
Murdoch believes a sustainable growth coalition might be the right approach, with small groups doing research and obtaining independent expert advice to present to the fast-track panel. People were unhappy with what was going on.
With the developer now in receivership, the consent application sits with the Environmental Protection Authority while the receivers work through the company’s assets. The notice does not indicate whether the Mackenzie project will be sold, restarted or abandoned.
For suppliers and contractors who have worked on the Mackenzie proposal, the appointment of receivers shifts any claim from the developer to Teneo, which now controls the company’s assets on behalf of Aquila. The receivership notice does not state what funds are available or how creditors will be treated.
For other renewable developers in the district, the case reminds them that fast-track consent carries obligations, including paying for the expert evidence a panel requires. The Environmental Protection Authority suspended this application over unpaid invoices, and the project has not progressed since.
Local businesses in and around Twizel, many of them reliant on the district’s landscape for tourism and farming, have been watching the solar proposals closely. The community group’s push for landscape overlays and independent advice targets the remaining applications, not just this one.

NZ Business News reports on the decisions, deals and numbers shaping New Zealand business — the companies making them, the policy and market conditions they work within, and what it means for the people running businesses here.